On a Queensland renovation over $3,300, the deposit is generally capped by law: 10% of the contract price, or 5% once the contract reaches $20,000. After that, payments should be tied to stages of work that are actually finished, so what you've paid stays close to what's on site. In most cases you also have 5 business days after receiving the signed contract to change your mind.
Naik's Renovations · Before you sign

Sally at the Naik's Renovations office desk
What does the law say about deposits?
A contract for residential building work over $3,300 is a regulated contract, and one worth $20,000 or more is a level 2 contract. On a level 1 contract the deposit can't be more than 10% of the price. On a level 2 contract it can't be more than 5%.
If your job is $20,000 or more, 5% is the number to remember. There's one exception, for jobs where most of the value is made off site, such as custom cabinetry, and the QBCC's deposits page explains it. The QBCC Commissioner's advice is to use licensed contractors, have a contract in place "regardless of the size of the job" and "never pay excessive deposit amounts".
How do progress payments work?
On our jobs, each payment is tied to a stage of the job, not to a date on the calendar. That way the money follows the work. If a stage hasn't been reached, the payment for it isn't due yet. The QBCC recommends the same thing, and says progress payments have to stay in line with the work done: a contractor can't claim more than 50% of the price, deposit included, until at least 50% of the work on site is complete.
For a bathroom, our stages look like this:
- 5% deposit, which includes the QBCC home warranty insurance premium
- 20% at commencement
- 25% when the sheeting is complete
- 25% when the tiling is complete
- 25% at final completion
Each stage is something you can see. Sheeting complete means the walls are up and ready for waterproofing. Tiling complete means the room looks like a bathroom again. The last payment comes when the job's finished.
What does the deposit actually do?
It locks in your start date. Once the deposit's paid, the job goes in the diary. From there we need your selections at least a week before we start, and longer if your tiles or custom cabinetry need to be ordered in. How a Naik's renovation runs goes through the whole sequence from the first call.
How long does a quote stay valid?
Ours hold for 30 days. Prices for materials and trades move, so a quote with no time limit is hard for anyone to hold to. If you need longer to decide, ask before the 30 days are up.
What happens if something changes once work starts?
It becomes a variation, and it should be agreed in writing before the extra work is done. The most common one on our jobs is timber damage. Water damage to timbers is the one thing we can't price before the old bathroom comes out, so it's excluded from the quote. If we find it, we talk it through with you: what's needed and what it'll cost.
Can I pull out after signing?
Usually, within the cooling-off period. On a regulated contract you can generally withdraw within 5 business days after you receive the signed contract. There are exceptions, and you'd normally pay the builder $100 plus reasonable out-of-pocket costs. The QBCC's cooling-off page sets out how it works, and on contracts of $20,000 or more you should also get the QBCC's Consumer Building Guide.
This is general information, not legal advice, and the QBCC recommends getting legal advice before you sign. If you're not sure how something in our quote or contract works, ring Sally on 0452 647 579 and ask before you sign.
From our jobs
In Thornlands we renovated a main bathroom with a leaking shower and changed the layout, about three and a half weeks on site in October 2026. See the Thornlands bathroom, read about our bathroom renovations, or see what a bathroom costs in the Redlands and how home warranty insurance works.
Sources
- QBCC, "Deposits and progress payments"
- QBCC, "Cooling-off period"
- QBCC, "Contract variations"
- Queensland Building and Construction Commission Act 1991, Schedule 1B s 33 (deposits)
- Queensland Building and Construction Commission Act 1991, Schedule 1B s 35 (cooling-off)
- Queensland Building and Construction Commission Act 1991, Schedule 1B ss 6 and 7 (contract levels)
- QBCC Regulation 2018 s 45 (level 2 amount, $20,000)
- QBCC news, 23 Dec 2024, "Building regulator warns home owners to protect themselves against unlicensed contractors"
Want a quote with the stages set out?
Sally is your first point of contact. She'll answer your questions and book a time for us to come out and see the room.
Want a quote with the stages set out?
Send your suburb, which rooms you're thinking about and a photo or two. Sally will call you to book a time for us to come out.
Or call Sally on 0452 647 579
SallyYour first point of contact
Let's talk about your vision
Step 1 of 5
The job